During the upcoming week, the contractor will continue excavation activities for the Abutment B cofferdam. Work will also continue on the installation of reinforcing steel and formwork for the wall section of Abutment A in preparation for a concrete pour scheduled for the early morning of Wednesday, November 25, 2026. On Wednesday, preparatory activities will begin at approximately 5:00 AM and will include construction vehicle movements and the use of work lights. Concrete placement is scheduled to begin at 6:30 AM.
No construction activities are planned for Thursday, November 26 or Friday, November 27, 2026, in observance of the Thanksgiving holiday.
A reminder regarding the footbridge: for everyone’s safety, bicyclists are encouraged to dismount and walk their bicycles across the structure. A designated detour for motorists remains in place.
All area businesses and facilities remain open.
Please be advised that construction crews and vehicles will continue to be active in the area while road work is underway. Although the Dry Bridge will be closed, motorists traveling near the construction zone should proceed with caution as construction activities continue.
For more information about this project, please visit LebanonNH.gov/DryBridge.
During the upcoming week, the contractor will continue excavation activities for the Abutment B cofferdam. Work will also continue on the installation of reinforcing steel and formwork for the wall section of Abutment A in preparation for a concrete pour scheduled for the early morning of Wednesday, November 25, 2026. On Wednesday, preparatory activities will begin at approximately 5:00 AM and will include construction vehicle movements and the use of work lights. Concrete placement is scheduled to begin at 6:30 AM.
No construction activities are planned for Thursday, November 26 or Friday, November 27, 2026, in observance of the Thanksgiving holiday.
A reminder regarding the footbridge: for everyone’s safety, bicyclists are encouraged to dismount and walk their bicycles across the structure. A designated detour for motorists remains in place.
All area businesses and facilities remain open.
Please be advised that construction crews and vehicles will continue to be active in the area while road work is underway. Although the Dry Bridge will be closed, motorists traveling near the construction zone should proceed with caution as construction activities continue.
For more information about this project, please visit LebanonNH.gov/DryBridge.